Project Management Oversight report highlights more than $7 billion in ongoing transit investments

March 8, 2023

22 RTA 0451

Twice a year the RTA publishes a Project Management Oversight (PMO) report that details major transit investments by CTA, Metra, and Pace and fulfills our oversight role in ensuring that we are efficient stewards of capital funding. There are 107 projects detailed in the December 2022 PMO report, representing more than $7.56 billion worth of construction, maintenance, and procurement to improve the Chicago region’s transit system. Read the full report.

Highlights from the latest PMO report include:

CTA: Non-Revenue 61st Street Rail Shop

Expected Completion: December 2023

Budget: $70,017,063

The purpose of this new project is to provide a place for storage, maintenance, and repair of over 125 pieces of equipment. This new facility is necessary as it is replacing a rail shop that was demolished in 2009. The new building will be approximately 70,000 sq. ft. and will address the various needs of non‐revenue rail equipment maintenance.

Metra: Harvey Transportation Center

Expected Design Completion: December 2023

Budget: $6,000,000

Metra is partnering with Pace for the reconstruction and rehabilitation of the Harvey Transportation Center on the Metra Electric Line. This project will include new station entrance, new platform headhouses and waiting areas, new elevators, and other upgrades that will create a better experience for public transit riders in the south suburbs.

Pace: New I-55 Garage – Plainfield

Completed December 2022

Budget: $55,385,593

Together, Pace and the Village of Plainfield have entered into an Intergovernmental Agreement (IGA) for the design and construction of a new Pace bus maintenance and storage facility. This new garage in Plainfield is necessary to support the growth of Pace’s I-55 Bus-on-Shoulder service. The construction of the facility has been completed in December of 2022 and Pace is currently running operations out of the new garage.

Together, the RTA and Service Boards report capital programs and expenditures which are detailed in the 2022 Project Management Oversight (PMO) report. Included in the details are the progress, schedule and budget for each active project.

Subscribe to our Newsletter

* indicates required
Type your email address here
What emails would you like to receive from the RTA
Tagged in: Capital Programming | PMO | Project Management Oversight | CTA | Metra | Pace | RTA

Related Articles

22 RTA 0451 Project Management Oversight report highlights more than $7 billion in ongoing transit investments

Twice a year the RTA publishes a Project Management Oversight (PMO) report that details major transit investments by CTA, Metra, and Pace and fulfills our ov...

March 8, 2023
22 RTA 1532 Understanding capital vs. operating funding and why it matters

Funding the second largest transit system in the country is a large and complicated task. It’s true, Chicagoland’s transit system is facing a $730 million an...

February 2, 2023
221107 RTA 1614 RTA to measure capital projects on equity, climate impacts, and more

The Chicago Region is home to one of the largest transit systems in the nation with approximately 1,500 miles of track, 7,500 vehicles, 400 stations, and 70 ...

February 2, 2023
22 RTA 0400 Chicago area transit agencies win federal grants to continue to improve, expand system

In 2023, Chicago area transit agencies will use millions in newly available federal transit funding to make the system more reliable, sustainable, and access...

January 13, 2023
22 RTA 0682 What is the ‘fiscal cliff’ and what can be done about it?

After more than a year of engagement, the RTA has released a draft regional transit strategic plan, Transit is the Answer, which the RTA Board of Directors w...

December 15, 2022
A young woman in a green sweater looks at her smartphone on a Metra train. The RTA launched a new website. Explore it now.

Today, the RTA launched a new website featuring a refreshed brand for the agency representative of a forward-looking vision for the region’s transit system. ...

November 14, 2022
RTA
CTA
Metra
Pace
Copyright © 2022 Regional Transportation Authority. All Rights Reserved.