Contact Contact

RTA oversight ensures transit projects are delivered on time, on budget

January 21, 2022

PMO Blog Header 1110x545 1

Throughout 2021, work to enhance the region’s transit system continued with 80 capital projects underway across CTA, Metra, and Pace that translated to $7.16 billion worth of investment. 

The RTA provides Project Management Oversight to ensure projects are delivered on time and on budget. “Our goal is to be efficient stewards of funding,” said Violet Gurgul, PMO Division Manager, who presented the latest PMO report to the RTA Board in December. All 80 projects are within budget. Of the 57 state-funded projects91 percent are on schedule despite disruptions caused by the COVID-19 pandemic. The projects will upgrade and maintain transit infrastructureas well as enhance customer experience, safety, and security. 

Projects highlighted in the December 2021 report include:  

CTA: Austin Station  


  • Expected completion: January 2024  
  • Budget: $26.5 million




CTA is beginning work on the renovation and expansion of the stationhouse at Austin Boulevard. The Green Line Austin station is part of CTA’s All Stations Accessibility Program (ASAP).

The project will include an ADA compliant ramp between the street level and the stationhouse, add an elevator connecting the stationhouse to the platform, remove an existing escalator to accommodate a larger platform for wheelchair accessibility, and the installation of new sidewalks, curb ramps, accessible parking, and crosswalks.

The project will also renovate and expand the Mason Avenue stationhouse, reopen its exit and stairs to the platform, and add new signage, security cameras, and lighting upgrades.

The Austin stationhouse is eligible for the National Register of Historic Places, so the project includes hiring an architecture consultant to help preserve the station’s historic nature.

Metra: Union Pacific North Line Bridges


  • Expected completion: May 2028
  • Budget: $162.1 million


Metra is starting the design for the replacement of 11 century-old bridges on the Union Pacific (UP) North Line from Cornelia Avenue southward to Fullerton Avenue, and the rehabilitation of the Addison Street bridge. While still safe to use, these bridges are over 100 years old, show signs of increased deterioration, and have exceeded their lifespan. This project is a continuation of previous efforts to replace aging bridges on the UP-North Line. The northern bridges were fully replaced in the first phase of this project, which was completed in September of 2021. These new bridges are built to last for another century, which will increase both reliable service and safety.



Pace: ADA Technology Upgrades and Transfer Centers


  • Expected Completion: December 2022
  • Budget: $4.2 million




Pace has acquired land for a new ADA transfer center in Schaumburg. The former USPS site will be adjacent to the Northwest Transportation Center and will provide connections to fixed‐route services in addition to ADA paratransit services. Additionally, ADA‐related improvements will be completed, including technology updates to enhance access for customers.

The RTA and Service Boards are committed to creating a more accessible, safe, and equitable transit system for the six counties of Northeastern Illinois.

The financial need to modernize the region’s robust transportation network exceeds the funding available. The 2022 Regional Transit Budget identifies priority projects for the future, many of which remain unfunded. The RTA will continue to collaborate with its partners to advocate for sustainable transportation funding solutions.

In its efforts to increase transparency around transportation investments, the RTA publishes a PMO report twice a year. Read the June 2021 report, spotlighted on the agency’s blog six months ago. To keep up to date with what’s happening in transit locally, subscribe to the Connections blog.

For more information and data about transit projects and studies happening in Chicago, search RTAMS (Regional Transportation Authority Mapping and Statistics) at https://www.rtams.org/transit-projects-and-studies.

Subscribe to our Newsletter

* indicates required
Type your email address here
What emails would you like to receive from the RTA
Tagged in: Capital Programming

Related Articles

22 RTA 1020 CTA and Pace offer alternatives during rebuild of Forest Park Branch of Blue Line

On July 23, the CTA began Phase I of their multi-year, multi-phased project to make service along the Blue Line’s Forest Park Branch faster, safer, more reli...

August 10, 2023
22 RTA 0400 CTA, Metra, and Pace Accelerating Efforts to Electrify Fleets

Riding public transit is one of the most sustainable modes of travel, and the transit system is one of the strongest tools our region has in the fight agains...

July 31, 2023
Webinar 4 Transportation Tuesday recap: Advancing a Regional Capital Strategy

One of the core responsibilities of the RTA is to work with the CTA, Metra, and Pace to advance a capital strategy that ensures major transit investments are...

June 28, 2023
PMO RTA releases semi-annual project management oversight report highlighting over $7 billion in transit investments

Under its Project Management Oversight (PMO) program, the RTA ensures that the Service Boards—CTA, Metra, and Pace—are spending capital funds and managing th...

June 23, 2023
22 RTA 0451 Project Management Oversight report highlights more than $7 billion in ongoing transit investments

Twice a year the RTA publishes a Project Management Oversight (PMO) report that details major transit investments by CTA, Metra, and Pace and fulfills our ov...

March 8, 2023
22 RTA 1532 Understanding capital vs. operating funding and why it matters

Funding the second largest transit system in the country is a large and complicated task. It’s true, Chicagoland’s transit system is facing a $730 million an...

February 2, 2023
RTA
CTA
Metra
Pace
Copyright © 2022 Regional Transportation Authority. All Rights Reserved.